Main Street

Background

Main Street is the center of downtown Rogers and one of the oldest parts of town. However, with this history come existing utilities that are no longer adequate and almost all are nearing the end of their life cycles. The Main Street Reconstruction Project will replace existing sewer, watermains and storm sewers with new and in some cases larger systems to accommodate our growing population. Along with the replacement of City utilities, the Public Works Department worked with the internet and cable providers in the area to move existing overhead wires to underground, which was completed in late 2020. The overhead electrical wires are to be moved underground this year, with subsequent removal of electrical poles. This move is intended to make Main Street safer and more aesthetically pleasing.

 

Project Map & Location

Updates

Due to delays in the agreement with Hennepin County regarding giving back ownership of Main Street to the City, construction will be delayed until further notice.

Timeline

Reconstruction of Main Street will be delayed until Main Street can be given back to the City, expected construction to start when agreement reached.

Key Documents

 

David Koch/134th Ave N (PMP)

Background

Starting in late July, David Koch Ave and 134th Ave N are looking to have improvements done. The planned improvements will include miscellaneous curb and gutter repair on 134th Ave and David Koch Ave, pavement removal and regrading on David Koch Ave, milling top layer of bituminous on 134th Ave and Weinand Cir, and new pavement on all three portions of the project. This work will help extend the lifecycle of these streets and make driving on these roads smoother.

Project Map & Location

Updates

  • Week 1 (July 24 – July 28): Construction started this week with installing erosion control and spot curb and gutter and driveway removals on David Koch Avenue

  • Week 2 (July 31 – August 4): The Contractor continued spot curb and gutter replacements and began milling the existing roadway surface on David Koch Avenue.

  • Weeks 3 & 4(August 7 – August 18): The Contractor started grading the roadway in preparation for the first layer of bituminous pavement on David Koch Avenue.

  • Week 5 (August 21 – August 25): The Contractor installed the first 2 layers of bituminous pavement on David Koch Avenue. The contractor began grading the gravel shoulders and started restoration work.

  • Week 6 (September 4 – September 8): The Contractor completed the final layer of pavement and installed pavement striping on David Koch Avenue.

  • Week 7 (September 11 – September 15): The Contractor completed spot curb and gutter and driveway replacements on 134th Avenue.

  • Week 8 (September 18 – September 22): The Contractor will mill the existing roadway surface on 134th Avenue. This process consists of grinding up the top layer of bituminous and hauling it offsite. On Saturday, September 23rd, 134th Avenue will undergo the final paving of bituminous surface.

  • Week 9 (September 25 - September 29) The contractor will pave the final bituminous surface on 134th Avenue on Saturday, September 30th.

  • Week 10 (October 1-October 6): Work has been finished, final touches and inspections were done.

Timeline

  • April 21, 2023 - Project Bid Opening

  • May 9, 2023 - Project awarded to Omann Contracting Companies, Inc. by the City Council

  • July 2023 - Start of construction on David Koch Avenue

  • September 2023 - Construction substantially complete on David Koch Avenue

  • September 2023 - Start of construction on 134th Avenue

  • October 2023 - Construction substantially complete on 134th Avenue

Key Documents

 

Maple Ave/Sugar Ln (PMP)

Background

Street maintenance is planned for the Maple Ave Neighborhood. The planned improvements for this project will include miscellaneous curb and gutter replacement, miscellaneous driveway work, milling of the existing pavement, and new bituminous pavement. This work will help extend the lifecycle of these streets and make driving on these roads smoother.

Project Map & Location

Updates

  • Week 1 (September 18 – September 22): Construction started with installing erosion control and saw-cutting at curb replacement areas.

  • Week 2 (September 25- September 29) The contractor will begin spot curb and gutter and driveway replacements. The contractor will also be replacing 2 storm structures that needed repairs.

  • Week 3 (October 1-October 6): Work has been finished, final touches and inspections were done.

Timeline

  • June 29, 2023 - Project Bid Opening

  • May 11, 2023 - Project awarded to ASTECH Corp by the City Council

  • September 2023 - Start of construction

  • October 2023 - Construction substantially complete

Key Documents

 

Fletcher Lane Improvements

Background

With the addition of the Fletcher By-Pass, the gravel portion of Fletcher Lane will be changed and Fletcher Lane will be shortened to just north of the railroad tracks. This dead end will then be turned into a cul-de-sac.

Project Map & Location

Updates

Updates coming soon!

Timeline

Construction is scheduled for 2022.

Key Documents


Fletcher By-Pass Phase I

Background

A planned road, Fletcher By-Pass, will extend CO RD 116 to CO RD 81 replacing the existing City owned Fletcher Lane. Fletcher By-Pass will have four lanes and contain a railroad crossing, multi-use trails and traffic signals. As of early 2021 this project is still in the planning phase and the City is coordinating efforts to obtain right of way from land owners in the area.

Project Map & Location

Updates

Updates coming soon!

Timeline

Design for this project is expected to happen during early-mid 2024. Construction is expected to occur late 2024-late 2025.

Key Documents


Cambria Farms (PMP)

Background

Street maintenance is planned for the Cambria Farms Neighborhood. The planned improvements for this project will include miscellaneous curb and gutter replacement, miscellaneous driveway work, removal of the existing pavement, minor grading of the roadway, and new bituminous pavement. This work will help extend the lifecycle of these streets and make driving on these roads smoother.

Project Map & Location

Updates

  • Week 1 (September 4 – September 8): Construction started this week with installing erosion control and spot curb and gutter and driveway removals.

  • Week 2 (September 11 – September 15): The Contractor completed spot curb and gutter and driveway replacements.

  • Week 3 (September 18 – September 22): The Contractor will remove the existing roadway surface, grade the roadway and install the first lift of bituminous pavement.

  • Week 4 (September 25-September 29): The contractor will pave the final lift of bituminous pavement, grade the aggregate shoulder and hydroseed impacted project areas.

  • Week 5 (October 1-October 6): Work has been finished, final touches and inspections were done.

Timeline

  • April 28, 2023 - Project Bid Opening

  • May 9, 2023 - Project awarded to Park Construction Company by the City Council

  • September 2023 - Start of construction

  • October 2023 - Construction substantially complete

Key Documents